A programme of surface dressing on roads across Hambleton will start this month.
The work by North Yorkshire County Council aims to prolong the life of treated roads.
Among work this month will be drainage investigation works on Jubilee Road and Bedale Road, Aiskew, which are programmed to begin on 18 May and last for 10 days, Monday to Friday.
Nigel Smith, head of highway operations, said: “The safety of the public, along with our employees and contractors is paramount.
“Therefore, in all the highways work we undertake during the current Covid-19 restrictions we ensure that guidance on social distancing is observed.
“A consequence of ensuring social distancing is that there will not be letter drops to properties in areas where surface dressing is to take place, but information boards will be erected in advance in locations where work is to take place.”
For more information about surface dressing, including what to do if surface dressing takes place on your street, visit www.northyorks.gov.uk/surface-dressing.
A schedule of roads to be treated in the surface dressing programme is below.
The work is subject to weather conditions, so the dates below are subject to change.
Hambleton
Moxby Lane, Sutton on the Forest Wed 29/07/20 Thu 30/07/20 Cornbrough Road, Sheriff Hutton Thu 30/07/20 Thu 30/07/20 Helperby Main Street, Helperby Thu 30/07/20 Thu 30/07/20 Amplecarr, Husthwaite Thu 30/07/20 Fri 31/07/20 Hornby Village Street, Hornby Fri 14/08/20 Fri 14/08/20 Danby Wiske Village Street, Danby Wiske Fri 14/08/20 Fri 14/08/20 Church Lane, Worsall Sun 31/05/20 Sun 31/05/20 Haggitt Hill Lane, East Rounton Sun 31/05/20 Mon 01/06/20 East Rounton Village to junction with Brickyard Plantation, West Rounton Mon 01/06/20 Mon 01/06/20 Quarry Lane, Osmotherley Mon 01/06/20 Tue 02/06/20 Woundales Lane, Borrowby Tue 02/06/20 Tue 02/06/20 Ingdale Lane, Kirby Knowle Tue 02/06/20 Tue 02/06/20 Knowle Lane, Kirby Knowle Tue 02/06/20 Wed 03/06/20 Ewelands Hill, Felixkirk Wed 03/06/20 Thu 04/06/20 Town Street / Main Street, Whenby Fri 05/06/20 Mon 08/06/20 Ings Lane, Stillington Mon 08/06/20 Mon 08/06/20 Northallerton Road, Thirsk Tue 09/06/20 Tue 09/06/20 Green Lane, Maunby Wed 10/06/20 Wed 10/06/20 Bramper Lane, Thrintoft Wed 10/06/20 Wed 10/06/20 South Moor Lane, Sowerby Wed 10/06/20 Thu 11/06/20 A19, Thirkleby Thu 11/06/20 Fri 12/06/20 Water Lane, Dalton Fri 12/06/20 Sat 13/06/20 Church Lane, Hutton Sessay Sat 13/06/20 Sat 13/06/20 Moor Road, Knayton Mon 06/07/20 Mon 06/07/20 Fanny Lane, Knayton Mon 06/07/20 Mon 06/07/20 Town Street / Main Street, Whenby Mon 06/07/20 Tue 07/07/20 Catton Lane, Topcliffe Tue 07/07/20 Wed 08/07/20 Sinderby to Ainderby Quernhow from junction with B6267 to Holme junction, Sinderby Wed 08/07/20 Thu 09/07/20
The county council is also about also about to begin pre-surface dressing patching works in the Hambleton district on roads that will be surface dressed in the 2021/22 financial year.
These include:
Mile House Farm to White Cross Bedale 11th May 12th May Long Lane Well 13th May 3rd June Nosterfield to Thornborough Nosterfield 4th June 5th June Sinderby to Holme on Swale Sinderby 8th June 8th June Northallerton Road Thirsk 9th June 10th June Newby Wiske Village Streeet Newby Wiske 11th June 12th June Station Road South Otterington 15th June 16th June Whittiaker Hill to Thornton Le Beans Thornton Le Beans 17th June 19th June Cotcliffe Bank – from crossroads to to A19 Northallerton 22nd June 25th June Chester Lane Kirby Sigston 26th June 6th July Banks Road – from A684 to Bullamoor Brompton 7th July 20th July Hornby Road Appleton Wiske 21st July 23rd July Stokesley Road Hutton Rudby 24th July 28th July Ingleby Greenhow to Great Ayton Ingleby Greenhow 29th July 31st July Ingleby Greenhow to Easby Ingleby Greenhow 3rd August 13th August Battersby to Ingleby Greenhow junction Battersby 14th August 28th August New Row to Kildale Kildale 27th August 7th September Percy Rigg Cross to District Boundary Kildale 2nd September 3rd September Coxwold Village Street to Whinny Bank Kildale 2nd September 3rd September Coxwold to Oulston Coxwold 10th September 18th September Yearsley to Brandsby Yearsley 21st September 2nd October A19 south bound exit from northern roundabout and Easingwold Easingwold 5th October 5th October
Be the first to comment