Surface dressing programme to start on Hambleton roads

Surface dressing taking place. Photo: Michael Trolove.

A programme of surface dressing on roads across Hambleton will start this month.

The work by North Yorkshire County Council aims to prolong the life of treated roads.

Among work this month will be drainage investigation works on Jubilee Road and Bedale Road, Aiskew, which are programmed to begin on 18 May and last for 10 days, Monday to Friday. 

Nigel Smith, head of highway operations, said: “The safety of the public, along with our employees and contractors is paramount.

“Therefore, in all the highways work we undertake during the current Covid-19 restrictions we ensure that guidance on social distancing is observed.

“A consequence of ensuring social distancing is that there will not be letter drops to properties in areas where surface dressing is to take place, but information boards will be erected in advance in locations where work is to take place.”

For more information about surface dressing, including what to do if surface dressing takes place on your street, visit www.northyorks.gov.uk/surface-dressing.

A schedule of roads to be treated in the surface dressing programme is below.

The work is subject to weather conditions, so the dates below are subject to change.

Hambleton

Moxby Lane, Sutton on the ForestWed 29/07/20Thu 30/07/20
Cornbrough Road, Sheriff HuttonThu 30/07/20Thu 30/07/20
Helperby Main Street, HelperbyThu 30/07/20Thu 30/07/20
Amplecarr, HusthwaiteThu 30/07/20Fri 31/07/20
Hornby Village Street, HornbyFri 14/08/20Fri 14/08/20
Danby Wiske Village Street, Danby WiskeFri 14/08/20Fri 14/08/20
Church Lane, WorsallSun 31/05/20Sun 31/05/20
Haggitt Hill Lane, East RountonSun 31/05/20Mon 01/06/20
East Rounton Village to junction with Brickyard Plantation, West RountonMon 01/06/20Mon 01/06/20
Quarry Lane, OsmotherleyMon 01/06/20Tue 02/06/20
Woundales Lane, BorrowbyTue 02/06/20Tue 02/06/20
Ingdale Lane, Kirby KnowleTue 02/06/20Tue 02/06/20
Knowle Lane, Kirby KnowleTue 02/06/20Wed 03/06/20
Ewelands Hill, FelixkirkWed 03/06/20Thu 04/06/20
Town Street / Main Street, WhenbyFri 05/06/20Mon 08/06/20
Ings Lane, StillingtonMon 08/06/20Mon 08/06/20
Northallerton Road, ThirskTue 09/06/20Tue 09/06/20
Green Lane, MaunbyWed 10/06/20Wed 10/06/20
Bramper Lane, ThrintoftWed 10/06/20Wed 10/06/20
South Moor Lane, SowerbyWed 10/06/20Thu 11/06/20
A19, ThirklebyThu 11/06/20Fri 12/06/20
Water Lane, DaltonFri 12/06/20Sat 13/06/20
Church Lane, Hutton SessaySat 13/06/20Sat 13/06/20
Moor Road, KnaytonMon 06/07/20Mon 06/07/20
Fanny Lane, KnaytonMon 06/07/20Mon 06/07/20
Town Street / Main Street, WhenbyMon 06/07/20Tue 07/07/20
Catton Lane, TopcliffeTue 07/07/20Wed 08/07/20
Sinderby to Ainderby Quernhow from junction with B6267 to Holme junction, SinderbyWed 08/07/20Thu 09/07/20

The county council is also about also about to begin pre-surface dressing patching works in the Hambleton district on roads that will be surface dressed in the 2021/22 financial year.

These include:

Mile House Farm to White CrossBedale11th May12th May
Long LaneWell13th May3rd June
Nosterfield to ThornboroughNosterfield4th June5th June
Sinderby to Holme on SwaleSinderby8th June8th June
Northallerton RoadThirsk9th June10th June
Newby Wiske Village StreeetNewby Wiske11th June12th June
Station RoadSouth Otterington15th June16th June
Whittiaker Hill to Thornton Le BeansThornton Le Beans17th June19th June
Cotcliffe Bank – from crossroads to to A19Northallerton22nd June25th June
Chester LaneKirby Sigston26th June6th July
Banks Road – from A684 to BullamoorBrompton7th July20th July
Hornby RoadAppleton Wiske21st July23rd July
Stokesley RoadHutton Rudby24th July28th July
Ingleby Greenhow to Great AytonIngleby Greenhow29th July31st July
Ingleby Greenhow to EasbyIngleby Greenhow3rd August13th August
Battersby to Ingleby Greenhow junctionBattersby14th August28th August
New Row to KildaleKildale27th August7th September
Percy Rigg Cross to District BoundaryKildale2nd September3rd September
Coxwold Village Street to Whinny BankKildale2nd September3rd September
Coxwold to OulstonCoxwold10th September18th September
Yearsley to BrandsbyYearsley21st September2nd October
A19 south bound exit from northern roundabout and EasingwoldEasingwold5th October5th October